17 March 2015 - 13:21
  • News ID: 237382
Gas Delivery up

TEHRAN March 17(Shana)--Gas transfer by District 1 hit 28.7 bcm over the first 11 months of the current Iranian calendar year since March 21 2014, up by six percent against the similar period last year, director of Gas Transfer District 1 Abdolhosian Koutki said.

In statements to Shana Koutki said gas delivery to Bidboland gas processing plant reached 7.8 bcm during the mentioned period, up by 11 percent against similar period last year, while gas transfer by IGAT_1 hit 7.9 bcm, up by 147 percent.

District 1 has also conducted detecting leakage operations in 3,900 km and pig running in 1.135 km of pipelines, up by 38 percent against similar period last year.

These operations will raise sustainability of gas flow, Koutki concluded.