Furthermore, he said, Phases 15 &16 will also become fully operational by the end of the current calendar year to March 2016.
He said Platform C of Phase 19 is prioritized to be completed by winter, adding pipelaying operations for the platform are finished and it is being prepared for pre-startup stage.
Two refinery trains of the phase with offshore feedstock supply will come on-stream by the end of the year provided that the financing of the projects take place as planned, he said.
Once completed, Phase 19 will produce 56.6 million cubic meters of sour gas.
This development phase was awarded by Pars Oil and Gas Company (POGC) to a Petropars-led consortium of Petropars Limited and Petropars Iran and Iranian Offshore Engineering and Construction Company (IOEC) in June 2010 under an engineering, procurement, construction (EPC) contract.
South Pars, when fully developed, would be producing more than 800 mcm/d in three years.