21 June 2017 - 15:50
  • News ID: 277329
Drilling Operations Complete at 3 South Pars Platforms

TEHRAN, June 21 (Shana) -- Drilling operations at platforms 22, 24A and 24B of the supergiant South Pars Gas Field are 100% complete, operator of the projects said.

 

Operator of SP. 22, 23 and 24 projects Farhad Izadjou said the drilling operations at platform 23 have made 80.4% progress so far. 

He said now that the drilling operations are over the projects are waiting for the delivery of CRA pipes for installation at the platforms. 

He said platforms 24A and 2 and 24B are satellite platforms and are connected to platforms 22 and 23 of the gas field, adding drilling of 11 wells at platform 22 an 8 wells at the satellite platform 24A. 

Izadjou further said the topside of Phase 22 has made 89% progress and will be installed as the first platform of the phase. 
News ID 277329

Your Comment

You are replying to: .
0 + 0 =