Mohammad Reza Chalipa said the two phases are now supplying 2,600 tons of butane and propane on a daily basis which is stored at the storage facility of the projects.
He said the first liquefied petroleum gas (LPG) cargo of the phases was also exported recently.
The two phases have so far produced 19.5 million barrels of gas condensate, he added.
Chalipa further said the projects has also yielded 21 billion cubic meters of methane, 627,000 tons of ethane and 11,900 tons of sulfur.
The phases have also supplied an average of 2,300t/d of ethane to petrochemical facilities for processing.